Summary: Reconstruction of pavement and incidental drainage improvements from bridge over floodway to Broadway.
Details: Storm sewer and turn lane improvements from Seneca.
Estimated Completion Date: Spring 2019
Updates: 03/15/2019 Cornejo crews have been working diligently to get everything done but unfortunately the weather is still the source of delays. Conditions to pour the surface of the road have to be dry and above 50 degrees and we just aren't seeing those conditions yet.
Traffic is open west of High Point. Local resident access only between Broadway and High Point.